Supervising Organization at the Provincial Level:
Development and Reform Commission of Guangdong Province
Scope and Scale of Project:
Production of diesel engines for low-speed ships in South china, manufacturing of key parts and components of diesel engines, construction of related outfitting facilities, and construction of a supporting public logistics pier for the CSIC base.

GuangZhou Longxue Shipbuilding
Time of Planning and Construction: 2008-2015
Total Investment: RMB 6 billion
Progress Schedule for 2011 and 2012:
The first phase of the Marine Engineering Equipment Zone will be completed by the end of 2011, and the second phase of the zone is expected to begin in 2012.